| Completed |
 |
Armed Forces Reserve Center - Ft. Sill, Oklahoma 125,000 sq. ft two story building. The Structural Steel Design, Detailing and Steeel Fabrication in less htan four and a half months. |
 |
Interstate Sign - Thackerville, OK 112 ft tall, 60 ft wide sign that supports six LED Monitors. |
 |
Medical Office Building - Duncan, Oklahoma Three Story Medical Office Building, 195 tons of structural steel. |
 |
New Processing Facility - Saginaw, TX 10,400 sq. ft Meat Processing Facility. The facility will operate at between 20 and 24 degrees Fahrenheit. |
 |
Rockwall Commons - Dallas, TX Speed Steel provided a Value Engineering Package that saved the Owners $140,000. |
 |
Bowman Building - Grapevine, TX 25,000 sq ft office building, design to substantial completion in “10 Weeks”. |
 |
In-Patient Tower - Livingston, TX 1200 ton, 6 story hospital, completed under budget and on schedule. Speed Steel provided price protection in a volital steel market. |
 |
Medical Arts Pavilion - Lufkin, TX Three story, 65,000 sq ft medical office building that Speed Steel accelerated the schedule by "10 weeks". |
| In Progress |
 |
METC Athletic Complex - Ft. Sam Houston, TX 43,000 sq ft athletic complex, 217 tons of structural steel. |
 |
Starship Dinning Halls - Ft. Sill, Oklahoma Two 64,000 sq. ft Dinning Halls, deliver steel in 4 months from project award date. |
|
|