Project Status: Completed Project Highlights: Two 64,000 sq. ft Dinining Halls Rapid Schedule 425 tons of structural steel Owner: U.S. Army Architect: CSCA Architects San Diego, CA Contractor: Harper Construction San Diego, CA | ![]() The schedule on this project is extremely critical. These dining halls have to be operational prior to converting the old dining halls to some much needed classroom space. To facilitate this Fast Track project, Speed Steel is using its full resources to ensure a successful delivery. The structural steel detailing was performed in conjunction with the structural and architectural designs. The detailing was completed and drawings were issued for approval just a few days after completion of the design drawings. Speed Steel Design Build will deliver the structural steel for this project four months after the project was awarded. This is due to seamless integration of our team. |